Back to Projects

Airfield Road Development

$16 million Kauri Landing Property Limited

ABOUT THE PROJECT

Kauri Landing Property Limited:  $16 million 

The project involved constructing a subdivision in 4 Stages for 210 houses on 8 hectares of peat. 

 

We imported 40,000m3 of peat fill from a nearby project, once our preload settlement had settled and the Geotechnical Engineer gave us approval to remove the preload, we proceed to start building the subdivision installing the stormwater drainage then roading and installing all the utilities, and concrete works as well as house platform pads.

 

3 km of deep stormwater was installed, ranging from 225mm to 1350mm.

Imported and placed 40,000m3 of fill.

We used our GPS Excavators to trim the fill and place 300mm Gap 40 Hardfill on the building planforms. 

We installed over 3km of utilities services which included watermain, low presser sewer, communications, power and street lighting.

We had to finish each stage with all QA sign off before the builders could take possession of each stage and build houses.